PMP美国项目管理认证的模拟考试的样题7(1)

日期:05-26 22:25:45 | 项目管理师考试 | 浏览次数: 167 次 | 收藏

标签:项目管理师考试试题,历年项目管理师考试真题,http://www.gaofen123.com PMP美国项目管理认证的模拟考试的样题7(1),
ans:  a  

14.  standard  of  purchased  material:  
a.  simplifies  inventory  control  
b.  reduces  the  risk  of  obsolescence  
c.  reduces  cost  of  purchasing  and  storage  
d.  all  of  the  above.  
e.  a  and  c  only.  
ans:  e  

15.  the  "control  points"  in  the  work  breakdown  structure  used  for  isolated  
assignments  to  work  centers  are  referred  to  as:  
a.  work  packages.  
b.  subtasks.  
c.  tasks.  
d.  code  of  accounts.  
e.  integration  points.  
ans:  c  

16.  the  utility  of  work-based  schedules:  
a.  reveals  interdependencies.  
b.  facilitates  "what  if"  exercises.  
c.  highlights  critical  activities.  
d.  provides  information  on  resource  requirements,  time  requirements  and  
tradeoffs.  
e.  all  of  the  above.  
ans:  e  

17.  the  way  a  project  manager  sends  and  receives  information  depends  upon:  
a.  how  others  relate  to  the  project  manager  
b.  the  project  manager’s  level  in  the  organizational  hierarchy  
c.  the  size  and  nature  of  the  project  
d.  the  project  manager’s  salary  and  age  
e.  the  number  of  projects  going  on  at  one  time  in  the  pany  
ans:  a  

18.  uncertainty  refers  to  a  situation  where:  
a.  the  oues  are  known  but  their  probabilities  are  high  
b.  the  oues  and  their  probabilities  are  known  
c.  neither  the  oues  nor  their  probabilities  are  known  
d.  states  of  nature  can  change  at  any  time  
e.  probabilities  of  various  states  of  nature  can  change  at  any  time  
ans:  c  

19.  which  of  the  following  is  closet  to  deming’s  definition  of  quality:  
a.  conformance  to  requirements.  
b.  fitness  for  use.  
c.  continuous  improvement  of  products  and  services.  
d.  customer  focus.  
e.  all  of  the  above.  
ans:  c  

20.  it  is  useful  to  conduct  project  risk  assessment  according  to  the  project’s  
a.  charter  
b.  statement  of  work  
c.  work  breakdown  structure  
d.  work  
e.  budget  
ans:  c  