qustions 1:
the purpose of project plan development is to--
a.
creat a document to guide project execution and control
b. document project assumptions and contraints
c. promotemunication among stakeholders
d. define key project reports
qustions 2:
overall change control is primarily concerned with-
a.
influencing factors that cause change, determining that change has occurred, and managing actual changes as they occur
b. maintaining integrity of baselines, integrating product and project scope, and coordinating change across knowledge areas
c. integrating deliverables from different functional specialties on the project
d. establishing a change control board that oversees the overall changes on the project
qustions 3:
the principal objective of project stakeholder management is to--
a.
identify all potential users of the project to ensureplete requirements analysis
b. thwart criticism of the project by developing a list of responses to known stakeholder concerns
c. be proactive in curtailing stakeholder activities that might adversely affect the project
d. build goodwill in the case of schedule and cost overruns
qustions4:
most of the project’s budget is expended during--
a.
project plan development
b. project plan execution
c. overall change control
d. project initiation
qustions 5:
assumptions generally involve some risk because-
a.
assumptions are based on lessons learned
b. historical information may not be available
c. assumptions are based on constraints
d. assumptions involve factors that are considered true, real, or certain
qustions 6:
all approved changes should be reflected in the--
a. performance measurement baseline
b. change management plan
c. quality assurance plan
d. project plan
qustions 7:
in project plan development, which of the following is not an organizational policy whose effects on the project must be considered?
a. constinuous improvement targets
b. status meetings
c. employee performance reviews
d. time reporting
qustions 8:
the output of project plan execution consists of --
a.
work results and change requests
b. project plan updates and corrective action
c. baseline changes and work authorization
d. additional planning and deliverables
qustions9:
the primary purpose of benchmarking is to--
a.
perform marking research to forecast how well a particular product will sell
b. measure products, services, and processes against those other organizations
c. understand and collect data on customer requirements to focus attention on meeting customer needs
d. determine performance targets
qustions 10:
change requests occur in all the following forms except--
a.
oral or written
b. legally mandated or optional
c. formal or informal
d. externally or internally initiated
+《美国项目管理PMP认证模拟考试试题精选1》相关文章
- 美国项目管理PMP认证模拟考试试题精选1
- › PMP美国项目管理认证考试的模拟题精选10
- › PMP美国项目管理模拟题精选9
- › PMP美国项目管理模拟题精选8
- › PMP美国项目管理认证模拟题精选7
- › PMP美国项目管理认证考试模拟题精选6
- › PMP美国项目管理认证样题4(1)
- 在百度中搜索相关文章:美国项目管理PMP认证模拟考试试题精选1
- 在谷歌中搜索相关文章:美国项目管理PMP认证模拟考试试题精选1
- 在soso中搜索相关文章:美国项目管理PMP认证模拟考试试题精选1
- 在搜狗中搜索相关文章:美国项目管理PMP认证模拟考试试题精选1